The works will finish manifold storm today, and will be put into service this week. (02/05/2016)

The Town Planning visits the storm drain in ave.

Placido Domingo at the intersection with the River Guadalentín Torre-Pacheco Street.

The work of collecting rainwater out to tender by open by the amount of 27,373 € procedure, and has been awarded after a bidding deadline of 26 days with an amount of € 16.278,94.

Councilman Galindo Rosique been proven in morning work the works of storm drain that began on April 20 and will end on the day;

POS starting work with conditioning and implementation of a new roundabout.

The collector collects water from the park of the Constitution, crosses the street Mateo Cerezuela and the end of the street a grid that crosses this street width is placed.

The grid collect water and channeled to the manifold 1000 mm diameter.

This collector runs parallel to the street Guadalentín River and flows into the ravine park of the Constitution.

"In parallel, work on the storm drain, it will make the Plan of Works and Services 2015, consisting of regularizing traffic with a new roundabout at that intersection and back street paving Guadalentín River to the intersection with the street Tarragona "said the Town Planning.

Source: Ayuntamiento de Torre Pacheco

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información